Baker Roofing commenced work last week, on Tuesday 5/28, completing 18 garage roofs. As of the end of the day Friday 5/31, garage roofs were finished in the 582-593 close and 6 of the 12 units in the 570-581 close. During the week of 6/3, work will continue in the following sequence: the remaining 6 units in 570-581, 594A-F, 595A-F and 596A-F.
Baker Roofing will inform residents with door hangars 1-2 days in advance of the expected work dates pending weather conditions. Baker Roofing will also be placing pallets of shingle materials in the upcoming closes to be worked, several days ahead of their starting work.
Please refer to the general notifications posted earlier to our website for a general description of the work, sequential order of work by close, actions to be taken by residents, and contact information for the Baker Roofing project manager. Thank you to our residents for your patience and flexibility during this period. We also extend our appreciation for the quality of work and expertise being provided by Baker Roofing.