Weathersfield paving status update as of Tuesday morning,
October 19:
520-523 – Milling and paving completed 10/18. Open to vehicles 10/19.
524-529 – Milling completed 10/18, paving Tuesday 10/19. Open to vehicles 10/20.
546-551 – Milling on Tuesday 10/19. Vehicles moved by 9am. Paving may extend to 10/19 and open to vehicles 10/19 or 10/20.
558-569 and 570-581 entrance repairs – Tuesday/Wednesday 10/19-10/20. Vehicles may enter and exit with caution.
552-557 – Concrete work on curb/gutter Wednesday 10/20. Vehicles removed by 8am Wednesday. Localized paving blend from right side curb to drain on Monday 10/25. Vehicles allowed with caution.
582-593 – Concrete work on storm drains near 587 and sewer station access Wednesday 10/20. Vehicle traffic allowed with caution.
582-593 – Milling and paving Monday-Tuesday 10/25-26. Vehicles removed by 8am 10/25.
Please consider alternative parking locations in coordination with your neighbors in other closes not affected by paving, at the Gathering Place or via support from a Weathersfield friend or neighbor. Avoid parking on the street as construction equipment will be on these roads.
Thank you for your patience, flexibility and courtesy among all our residents to help accommodate each individual neighbor’s accessibility and activity during this time.
Bill Kearney, Weathersfield Board/Committee Chair,