Lawn Aeration in September

Aeration and overseeding of all grass areas will occur on Monday, September 9, 2019, weather permitting.  In preparation for this project, the grass areas may or may not be mowed during the week of September 2 due to the fact that Ruppert has advised they like to let it grow longer prior to aeration.  The grass will be mowed  before the aeration project.

Weekly Garage Roofing Update–June 14

During the week ending 6/14, with 2 no-work rain days, Baker Roofing completed 18 roofs for a total completion of 60 of 92 garage roof replacements.  The following garage roofs are finished: 582-593, 570-581, 594A-F, 595A-F, 596A-F, 558-569 and 540-545.  During the week of 6/17 work will continue, depending on weather, in the following sequence: 530-539, 524-529, 520-522 and 508-519.  

Baker Roofing is informing residents with door hangers 1-2 days in advance of the expected work dates pending weather conditions.  Baker Roofing will also be placing pallets of shingle materials in upcoming closes to be worked, ahead of their starting work dates.

Please refer to the general notifications posted earlier to our website (click here) for a general description of the work and actions to be taken by residents.  A reminder that the Baker Roofing on-site project manager contact is – Josh Bailey, 919-306-6380.  

Thank you to our residents for your patience and flexibility during this period.  We also extend our appreciation for the quality of work and expertise being provided by Baker Roofing. 

Week Two Update on WSG Garage Roofing Status

As of the end of this week (6/7), Baker Roofing completed 42 of 92 garage roof replacements.  Garage roofs are finished in the following closes: 582-593, 570-581, 594A-F, 595A-F and 596A-F.  During the week of 6/10, work will continue depending on weather in the following sequence: 558-569, 530-539, 524-529.  

Baker Roofing is informing residents with door hangers 1-2 days in advance of the expected work dates pending weather conditions.  Baker Roofing will also be placing pallets of shingle materials in upcoming closes to be worked, ahead of their starting work dates.

Please refer to the general notifications posted earlier to our website for a general description of the work, sequential order of work by close, and actions to be taken by residents. A reminder that the Baker Roofing project manager contact is – Josh Bailey, 919-306-6380.  

Thank you to our residents for your patience and flexibility during this period.  We also extend our appreciation for the quality of work and expertise being provided by Baker Roofing.  

An Update on WSG Garage Roofing and Status

Baker Roofing commenced work last week, on Tuesday 5/28, completing 18 garage roofs.  As of the end of the day Friday 5/31, garage roofs were finished in the 582-593 close and 6 of the 12 units in the 570-581 close. During the week of 6/3, work will continue in the following sequence: the remaining 6 units in 570-581, 594A-F, 595A-F and 596A-F.  

Baker Roofing will inform residents with door hangars 1-2 days in advance of the expected work dates pending weather conditions.  Baker Roofing will also be placing pallets of shingle materials in the upcoming closes to be worked, several days ahead of their starting work.

Please refer to the general notifications posted earlier to our website for a general description of the work, sequential order of work by close, actions to be taken by residents, and contact information for the Baker Roofing project manager.  Thank you to our residents for your patience and flexibility during this period.  We also extend our appreciation for the quality of work and expertise being provided by Baker Roofing. 

Pruning to Start on June 3

NOTE EARLIER START DATE THAN PREVIOUSLY ANNOUNCED

Pruning for shrubs in the front and side of the homes (up to the air conditioning units) will start on Monday, June 3, 2019, WEATHER PERMITTING. 

PLEASE DO NOT INTERRUPT THE RUPPERT WORKERS WITH ANY REQUESTS OR ISSUES.  CONTACT Hope Weber OR Peggy Akers WITH YOUR COMMENTS.

Any shrub(s) you do not want trimmed, please tag with the colored tapes that are placed on the bench in each close in a plastic bag.  Once a homeowner has used the tape, return it in the plastic bag to the bench for your neighbors to use.  The tapes will be collected after pruning is complete. 

Within 2 weeks following the pruning, please remove any tape that you have put on a bush.

Update on Garage Roofing Project

As previously communicated, garage roof replacement will begin Tuesday, May 28. The project is expected to take 3-4 weeks. Work times will include Monday-Friday between the hours of 8:00 AM – 6:00 PM, weather permitting.

To learn more, including the order in which roofs will be replaced and other important information, select “Notices” under the “Documents” pull down menu above or click here.

Garage Roofing Project

Garage roof replacement will begin in Weathersfield on or about May 28 and continue into June.  The contractor expects 2 days of work activity  in each close.  We will communicate specific timelines for work in each close prior to and during the project.  To learn more, including project information and recommendations for residents, select “Notices” under the “Documents” pull down menu above or click here.

Recent Updates

  • Due to the recent inclement weather, Ruppert will be very busy with storm cleanup in Weathersfield on Thursday, December 13.  Ruppert has also rescheduled light pruning for Thursday.  Large trees will be pruned by Davey Tree on Monday, December 17.
  • The agenda for the December 14 WSG Board Meeting has been updated to include reports by the Architecture and Buildings & Streets Committees.  The Manager’s Report for the month of December has also been posted.