Baker Roofing commenced work last week, on Tuesday 5/28, completing 18 garage roofs. As of the end of the day Friday 5/31, garage roofs were finished in the 582-593 close and 6 of the 12 units in the 570-581 close. During the week of 6/3, work will continue in the following sequence: the remaining 6 units in 570-581, 594A-F, 595A-F and 596A-F.
Baker Roofing will inform residents with door hangars 1-2 days in advance of the expected work dates pending weather conditions. Baker Roofing will also be placing pallets of shingle materials in the upcoming closes to be worked, several days ahead of their starting work.
Please refer to the general notifications posted earlier to our website for a general description of the work, sequential order of work by close, actions to be taken by residents, and contact information for the Baker Roofing project manager. Thank you to our residents for your patience and flexibility during this period. We also extend our appreciation for the quality of work and expertise being provided by Baker Roofing.
Pruning for shrubs in the front and side of the homes (up to the air conditioning units) will start on Monday, June 3, 2019, WEATHER PERMITTING.
PLEASE DO NOT INTERRUPT THE RUPPERT WORKERS WITH ANY REQUESTS OR ISSUES. CONTACT Hope Weber OR Peggy Akers WITH YOUR COMMENTS.
Any shrub(s) you do not want trimmed, please tag with the colored tapes that are placed on the bench in each close in a plastic bag. Once a homeowner has used the tape, return it in the plastic bag to the bench for your neighbors to use. The tapes will be collected after pruning is complete.
Within 2 weeks following the pruning, please remove any tape that you have put on a bush.
As previously communicated, garage roof replacement will begin Tuesday, May 28. The project is expected to take 3-4 weeks. Work times will include Monday-Friday between the hours of 8:00 AM – 6:00 PM, weather permitting.
To learn more, including the order in which roofs will be replaced and other important information, select “Notices” under the “Documents” pull down menu above or click here.
Drivers and walkers be aware that Duke Power crews will be working next week (May 13-17) trimming trees around lamp posts and electrical wires along Village Way between Swim & Croquet and the Smokehouse mail kiosk.
Garage roof replacement will begin in Weathersfield on or about May 28 and continue into June. The contractor expects 2 days of work activity in each close. We will communicate specific timelines for work in each close prior to and during the project. To learn more, including project information and recommendations for residents, select “Notices” under the “Documents” pull down menu above or click here.
Due to the recent inclement weather, Ruppert will be very busy with storm cleanup in Weathersfield on Thursday, December 13. Ruppert has also rescheduled light pruning for Thursday. Large trees will be pruned by Davey Tree on Monday, December 17.
The agenda for the December 14 WSG Board Meeting has been updated to include reports by the Architecture and Buildings & Streets Committees. The Manager’s Report for the month of December has also been posted.
Due to the snow today, First Choice Disposal is shifting all collections by one day. This means no Weathersfield pick-up tomorrow, Tuesday, December 11. Trash and recycling collection will be Wednesday, December 12.
These plans are subject to weather conditions and could change. You can keep up with the latest news on trash collections by checking this First Choice Disposal web page:
Current forecasts are for a wintery mix of rain, snow and ice coming overnight (Saturday, December 8) and into Sunday and Monday for our area. Chatham County provides current weather information news and updates. They also give links to sites which provide advice for getting ready for a storm and what to do during one. Keep checking the Chatham County website at: https://www.chathamnc.org/about-us/news-updates
The Berkeley office will be closed from FRIDAY, DECEMBER 21st through WEDNESDAY, JANUARY 2. The answering service will be fielding normal calls. Call the regular office number at 919-448-5150.
However, if you experience an emergency where property will be permanently damaged, first call 911 and then the emergency contact at 919-357-8091.
The WSG Board Meeting originally scheduled for Friday, September 14 has been postponed until next week. The meeting is rescheduled for Tuesday, September 18. It will be held at the Gathering Place from 2:00 p.m. to 4:00 p.m. A copy of the meeting agenda is posted here.