Beginning in February, address numbers will be posted on Weathersfield garages to better connect each garage with the corresponding residence address. A letter outlining the implementation process was recently emailed to Weathersfield residents. A copy of that letter is attached below.
Category Archives: Garage Project
Weekly Garage Roofing Update–June 14
During the week ending 6/14, with 2 no-work rain days, Baker Roofing completed 18 roofs for a total completion of 60 of 92 garage roof replacements. The following garage roofs are finished: 582-593, 570-581, 594A-F, 595A-F, 596A-F, 558-569 and 540-545. During the week of 6/17 work will continue, depending on weather, in the following sequence: 530-539, 524-529, 520-522 and 508-519.
Baker Roofing is informing residents with door hangers 1-2 days in advance of the expected work dates pending weather conditions. Baker Roofing will also be placing pallets of shingle materials in upcoming closes to be worked, ahead of their starting work dates.
Please refer to the general notifications posted earlier to our website (click here) for a general description of the work and actions to be taken by residents. A reminder that the Baker Roofing on-site project manager contact is – Josh Bailey, 919-306-6380.
Thank you to our residents for your patience and flexibility during this period. We also extend our appreciation for the quality of work and expertise being provided by Baker Roofing.
Week Two Update on WSG Garage Roofing Status
As of the end of this week (6/7), Baker Roofing completed 42 of 92 garage roof replacements. Garage roofs are finished in the following closes: 582-593, 570-581, 594A-F, 595A-F and 596A-F. During the week of 6/10, work will continue depending on weather in the following sequence: 558-569, 530-539, 524-529.
Baker Roofing is informing residents with door hangers 1-2 days in advance of the expected work dates pending weather conditions. Baker Roofing will also be placing pallets of shingle materials in upcoming closes to be worked, ahead of their starting work dates.
Please refer to the general notifications posted earlier to our website for a general description of the work, sequential order of work by close, and actions to be taken by residents. A reminder that the Baker Roofing project manager contact is – Josh Bailey, 919-306-6380.
Thank you to our residents for your patience and flexibility during this period. We also extend our appreciation for the quality of work and expertise being provided by Baker Roofing.
An Update on WSG Garage Roofing and Status
Baker Roofing commenced work last week, on Tuesday 5/28, completing 18 garage roofs. As of the end of the day Friday 5/31, garage roofs were finished in the 582-593 close and 6 of the 12 units in the 570-581 close. During the week of 6/3, work will continue in the following sequence: the remaining 6 units in 570-581, 594A-F, 595A-F and 596A-F.
Baker Roofing will inform residents with door hangars 1-2 days in advance of the expected work dates pending weather conditions. Baker Roofing will also be placing pallets of shingle materials in the upcoming closes to be worked, several days ahead of their starting work.
Please refer to the general notifications posted earlier to our website for a general description of the work, sequential order of work by close, actions to be taken by residents, and contact information for the Baker Roofing project manager. Thank you to our residents for your patience and flexibility during this period. We also extend our appreciation for the quality of work and expertise being provided by Baker Roofing.
Update on Garage Roofing Project
As previously communicated, garage roof replacement will begin Tuesday, May 28. The project is expected to take 3-4 weeks. Work times will include Monday-Friday between the hours of 8:00 AM – 6:00 PM, weather permitting.
To learn more, including the order in which roofs will be replaced and other important information, select “Notices” under the “Documents” pull down menu above or click here.
Garage Roofing Project
Garage roof replacement will begin in Weathersfield on or about May 28 and continue into June. The contractor expects 2 days of work activity in each close. We will communicate specific timelines for work in each close prior to and during the project. To learn more, including project information and recommendations for residents, select “Notices” under the “Documents” pull down menu above or click here.